In Telangana, operators of DG sets above 61 kW must install a certified RECD with 70 % PM capture, shift to gas, or shift to GSR 804(E) gensets, and connect the set to real-time monitoring. Sets above 800 kW need an air pollution control device.

Checked against the official orders on · latest order dated

The rule at a glance

Issued by
Telangana Pollution Control Board (TGPCB)
Covers
All operators of DG sets above 61 kW in Telangana. The RECD option covers in-use sets of 61 to 800 kW older than five years from manufacture and within their useful life of 15 years or 50,000 running hours, whichever comes first.
Deadline
Comply within one year of the circular of 20 March 2025, and submit a time-bound action plan within 60 days.
Testing
A certified RECD from a CPCB-approved manufacturer. The circular cites the CPCB list of certified manufacturers.
Enforcement
Non-compliance may attract environmental compensation.

What the order asks for

  1. 01Use a certified RECD from a CPCB-approved manufacturer with 70 % PM capture efficiency.
  2. 02Shift to gas-based generators.
  3. 03Shift to gensets that meet GSR 804(E) dated 3 November 2022.
  4. 04Install a real-time monitoring system that sends data every 15 minutes to the TGPCB server.

Above 800 kW: any suitable air pollution control device that complies with GSR 489(E) dated 9 July 2002.

This is the current TGPCB circular on DG sets.

Official documents

Common questions

Is an RECD mandatory for DG sets in Telangana?

In Telangana, operators of DG sets above 61 kW must install a certified RECD with 70 % PM capture, shift to gas, or shift to GSR 804(E) gensets, and connect the set to real-time monitoring. Sets above 800 kW need an air pollution control device.

Which DG sets are covered by the TGPCB rule?

All operators of DG sets above 61 kW in Telangana. The RECD option covers in-use sets of 61 to 800 kW older than five years from manufacture and within their useful life of 15 years or 50,000 running hours, whichever comes first.

What is the deadline to comply in Telangana?

Comply within one year of the circular of 20 March 2025, and submit a time-bound action plan within 60 days.

Who tests and certifies an RECD for Telangana?

A certified RECD from a CPCB-approved manufacturer. The circular cites the CPCB list of certified manufacturers.

This page summarises official orders for general guidance and is not legal advice. Orders change; confirm the current position with TGPCB before you act.

Related

Other states: Delhi NCR, Tamil Nadu, Karnataka, Andhra Pradesh, Puducherry, Goa, Maharashtra, Gujarat, Odisha, Jharkhand, Meghalaya, Madhya Pradesh, Jammu & Kashmir